Man, if we had a pound for every time someone asked how the
building was going….
So, in case you are one of those who haven’t asked recently
– the skinny is this:
1.
The Council took possession of 100 High Street
at the end of January 2014 – after much fun and games with the locks The Stove
agreed to leave the building temporarily whilst DGC undertake the first stage
of the building works required.
2.
It is anticipated that the final planning
permission will be through by the middle of May and that works will commence at
this time.
3.
The first stage works comprise new access for
people with disabilities, a lift, new toilet provisions, services for a café,
general repairs etc. If all goes to plan (haha) this will take 12 weeks
4.
So the very earliest The Stove will be allowed
back in the building will be September
5.
When we get back in we can begin our own fit out
and modifications to the building (aka Stage 2) – these will include the café,
integrated artworks, IT and AV equipment (hell yes!)
We will be partially open as soon as we get the keys back
from DGC – don’t ask us when we will be fully open (because Will says it is not
possible to estimate this) – but there is a sweepstake running on the opening
date – if you are interested in taking part – contact Colin via info@thestove.org